Testimonials | Links | Contacts | Email
 
  • Home
  •  
  • Turn Key
  •  
  • Engineering
  •  
  • Manufacturing
  •  
  • Installation


  • Airport Conveyors

    Brisbane International Airport Baggage Handling System

    PGC Controls was involved from start to finish in the design and commissioning of the whole system. The system comprises of 15 Allen Bradley PLC5 programmable logic controllers, a total of 5500 I/O with ethernet and data highway plus communications. The project took 2 years to final acceptance - opening 2 months ahead of schedule. Completed September 1997.

    P.G.C Controls carried out an extensive upgrade of Brisbane international airport Baggage handling control room system. Upgrading the SCADA system and control room networking. Replaced reporting system with Access database total redundancy system, utilising ODBC and Nett DDE data handling. Completion and acceptance for preliminary works March 20 1999.

    Maintenance and breakdown repairs, electrical and control, for Brisbane International and Domestic airport conveyor systems

      visitors